November 16 - We are pleased to report the Orthopaedic Unit is now open!  Click here to see more images and to learn more about the newly renovated unit that features private patient rooms!
October 27 - We are very pleased to report that construction on the 4E/Orthopaedic Unit is moving right along and is right on schedule to open in mid-November!

The wood paneling is up; the tiles are being placed in the bathrooms;the cabinetry is being installed; and the nursing station desks are in place!
 

September 30 - Over the past several months Lakewood Hospital has been conducting major renovations in the South Parking garage. Most of the work has been concentrated on the 1st floor, St. Charles entrance, the 2nd floor south section and the west stairwells. These renovations are nearing completion.

On Saturday October 3, 2009 the renovation project will enter a new phase of work, therefore it will be necessary to close the physician parking area adjacent to the Belle Avenue entrance. This section will be closed to parking for approximately 1 month.

Additional parking spaces will be reserved for physicians on the ground level ramp at the St. Charles entrance.

 

September 14 - We are still on schedule to open the newly renovated Orthopaedic Unit that will have private patient rooms this coming November!

As you can see by the picture, the ADA bathrooms in each room are being tiled and readied for the grand opening.

August 31 - Construction on 4E/Orthopaedic Unit is moving forward and on schedule. The drywall is being installed in the bathrooms and rooms. The Unit is expected to be completed this fall.

Additionally, we are proud to announce the endovascular suite is on schedule to be fully renovated by November. Final drawings are being completed, the lab and all ancillary equipment is ordered and awaiting delivery.
  August 17 - Construction on the 4E/Orthopaedic Unit is progressing. Currently, we are anticipating the Unit to open this fall! We will keep you apprised of the ongoing construction.
 
  August 10 - A $1.5 million renovation project is well underway in the south parking garage. Major construction is currently being done on the 1st and 2nd floors. Please be extra careful and drive slow when maneuvering throughout the garage. Thank you!
  August 3 -  The construction crew is working on the nursing station! The newly designed and expanded work areas within the nurse’s station will allow physicians and staff members improved access to computers and various hospital information systems.
   July 29 - Vision for Tomorrow accompanies patient lunches! Last week all patients began receiving a special tray liner with their lunch. The design featuring facts, photos and a special word search puzzle is designed to inform and build excitement for patients and visitors about the key components of this multi-year strategic plan.
  July 20 - The plumbing is being installed for the bathrooms that will be part of every private patient room.
  July 13 - The renovation and repairs to the hospital’s attached garage have begun! Certain areas of the garage are closed to parking and traffic patterns have been adjusted to accommodate the work.

 

July 7 - The nursing station is taking shape! The unit will enable our highly skilled staff to provide the best care for our patients who can recover in a new, modern environment.
  June 15 - Certain areas of the garage will be
closed to parking and traffic patterns will be adjusted to accommodate the work.
    June 8 - Major renovation and repairs to the hospital’s attached garage are part of our Vision for Tomorrow.
Beginning Monday, June 15, certain areas of the garage will be closed to parking and traffic patterns will be adjusted to accommodate the work. Construction continues on the Orthopaedic Unit.
June 1 - Construction has begun on our 4E Orthopaedic Unit! Drs. Manuel Martinez, Kenneth Chapman and Duret Smith join in the wall-breaking ceremony on 4E/Orthopaedic Unit on Monday, June 1.

The private patient rooms will include ADA (Americans with Disabilities Act) approved bathrooms with shower; a flat screen TV; oxygen, suction, blood pressure equipment hidden behind a wood panel; cabinets that will hold patient belongings, supplies, dirty linen; sinks in every room; a sleeper chair for family members who spend the night; increased adjustable lighting; wireless computer access; and computers in each room for nurse documentation.
If you would like to make a donation to benefit Vision for Tomorrow,
please call the Lakewood Hospital Foundation at 216.529.7009 or click here.








 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 